ADI 24K Cleanroom
The two-story, 45,000 SF cleanroom project started out with doing Pile Caps, then pour slabs over the caps. A unique aspect of the project was at the upper level, the SOMD was done with only lightweight concrete. Project Details City: Beaverton State: OR Size SF: 45,000 Yards of Concrete:1,336 CY Completion Date: April 2021, 2023…